NAME OF WORK:
Design review at Pakyong Airport for slope stabilization to maintain the uphill slope on the western side of the basic strip at pakyong Airport, Sikkim
CLIENT:Spar Geo Infra Pvt Ltd
PROJECT FEATURES
950 m long and almost 70 m high slope-stabilisation
work in very complex geology and high permeability.
SERVICES:
- Review of design and made several changes in design after slope failure
- Regular visit at site to resolve technical issues and supervise the execution of work
PROJECT SCHEDULE:6 months